§ 117-42. Easement requirements.  


Latest version.
  • All permanent stormwater management systems identified in the post-construction stormwater pollution prevention plan (SWPPP), including detention or retention basins, filter strips, infiltration systems, conveyance systems, and structures located outside of the right-of-way shall be designated as common areas or incorporated into permanent easements. For the purposes of access, monitoring, inspection, and general maintenance activities, an adequate easement width beyond the actual footprint of the stormwater quality management facility as well as a 20-foot-wide access easement from a public right-of-way to each BMP shall be provided. The easement requirements noted may be changed by the city as deemed necessary for specific cases.

(Ord. No. 5085, § 1(162.25), 12-4-2006)