§ 117-13. Permit requirements.  


Latest version.
  • Where required, no land user shall begin a land disturbing activity subject to this chapter without receiving prior approval of an improvement location permit. Improvement location permits shall be issued in accordance with the requirements of chapter 137, zoning. Permits may be issued specifically for land disturbing activities or in conjunction with planned improvements that require land disturbing activity. An improvement location permit shall be required as follows:

    (1)

    Light land disturbing activity: No permit required.

    (2)

    Moderate land disturbing activity: Permit required.

    (3)

    Significant land disturbing activity: Permit required.

(Ord. No. 5085, § 1(162.15), 12-4-2006)